Mining Sector Reform in India: Mining Leases with Pre-embedded clearances
08062020
- Rajesh Deoliya
[rajeshdeoliya@gmail.com]
To attract the investment in the mining sector, Government of
India and State Governments are doing mammoth work to erase the hurdles in
the way of commencement of mining operations. In recent past government of
India has brought about several amendments in Mines and Mineral (Development
and Regulation) Act-2015, Minerals (Other than Atomic and Hydro Carbons
Energy Minerals) Concession Rules- 2016 and also in the Environment (Protection)
Act,1986.These reforms will certainly help in bringing new investment because
a project proponent or successful bidder is assured about the support of
respective state government and it's authorities in commencement of project
within the stipulated timeline.
It is a fact that the contribution of mining sector in the GDP and employment is almost decreasing due to lack of new investment. According to the Federation of India Mineral Industries (FIMI), which in a report states that the mining industry’s contribution (excluding petroleum and natural gas) to India’s GDP in 2018/19 was pegged at 1.63%, down from a peak of 1.93% in 2012/13. In comparison, mining contributed 7.5% to South Africa's GDP and 6.99% to Australia's GDP. (Source: Mining Weekly, 27th January,2020) This is because we are not able to bring virgin areas into production.
To attract investment in the mining sector, year 2015 onward
drastic changes in the procedure of allocation of mining lease were made. The
then existing preferential right (First cum First Serve) clause in grant of
mineral concessions was scrapped for buoyant auction of mining lease. This change
brought transparency in the grant of mining leases and assured premium to
government in terms of revenue generation but the high payments to government
in bidding and delay in the projects
due to delay in grant of permissions, approvals and clearances made things
worst in favour of successful bidders.
The government has realized the issues and came up with an amendment by an order of Ministry of Mines, Government of India dated 03.06.2020 paving way for grant of some of the mining leases having pre-embedded clearances for mining projects (lease). Initially this will be a pilot project i.e each state government will identify 5 mineral blocks in pre-embedded mode and others in normal auction mode in which all the clearances will be obtained by successful bidder. |
The Pre-embedded clearances:
In general, the auction blocks require following clearances/
permissions for commencement of mining operation:
1. Forest Clearance
2. Wild life clearance/ The NoC from Wild Life
Conservator of Forest.
3. Mining Plan
approval
4. Environmental
clearance
5. Consent to
Establish
6. Consent to Operate
7. Explosive license
8. Mine
opening permission
9. Permission for installation / trail
operation of equipment
10. Ground water
clearance
11. Railway Siding
approval
12. Power line from
state DISCOM
13. Approval for diesel
storage
14. Clearances related
to the work under an existing transmission line or
shifting of the transmission line
15. Gram Sabha consent
16. NoC from Panchayat
Apart from these some more permissions are also required which
may also be part of pre-embedded clearances
17. Aravali Certificate
( applicable in Aravali Hill range areas)
18. NoC from revenue
records.
19. Transfer of
Government land and falling in the mining lease are
20. DGMS Permissions
21. Approval of
Rehabilitation / Resettlement plan
22. Social Impact
Assessment studies
23. Land Acquisition.
24. Stoppage of sale or
purchase of land in the mine block area to protect the interest of successful
bidder.
|
The Project Monitoring Unit (PMU):
In the newly proposed system pre-embedded permissions for a
mine block will be arranged by a PMU which will engage subject experts to
obtain permissions like approval of mining plan, environmental clearance, forest
clearance etc. The PMU will arrange the land rights for government as well as
private land which will be transferred to successful bidder.
The expenditure incurred by PMU / state government in
obtaining clearance will be charged from the successful Bidder.
|
The Pre- caution:
Since the PMU will be a government body and project will be
undertaken by a private body, precautions have to be taken in design of
project concept and project budget. A project seems viable to PMU may not be
viable to bidders.
ii) Issues of Project Concept and Viability:
The PMU has to do some preliminary work related to the project
concept and its viability. Say for example, the mining plan and environmental
clearance are production and technology specific, these are decided by a
project proponent based upon his experience with technology, market
conditions, financial capabilities, short term and long term business
planning etc, for entire mine life. In the absence of such knowledge, the
project concept designed by PMU may not be encouraging to project proponent
and rather may result in distraction.
iii) Issues in Production Design:
The successful bidder may require change in the mine
production immediately or after some time. The restriction of liberty of 25
percent change in the mine plan production is a limitation because if PMU
takes clearance at high production than it will be almost difficult for
project proponent to modify the business plan. A general tendency of a
project proponent is to keep mine production at minimum possible level for
first five year and then increase it in subsequent plan period in such a way
to extract the entire mineral in the remaining life of mine. Approaching
MoEFCC for change in production will again result in delay. For higher
production the state government may not raise any objection but for lower
production planning by successful bidder, the state government may not agree
because of anticipated loss of revenue and changes in the Mine Development
and Production Agreement (MDPA) which
is essential part of mine lease deed. Since the mine blocks are of commercial
nature a bidder may not find ample orders for disposal of higher mineral production
in the market. This will attract penalties, appropriation of performance
securities which may lead to cancellation of mine too. If successful bidder
decides for captive use then also the pre-decided production parameters may
not be attractive.
iv) Issues of Public Commitments:
In public hearing the state government will do all the
commitments on behalf of project proponent because project proponent will not
be part of public consultation process which may result in conflict between
successful bidder and community. This can be avoided by reasonable
commitments and giving liberty to the successful bidder to modify commitments
upon interaction with the community once project commences.
|
The Conclusion:
The above discussion may appear negative but it is only about
pre-cautions in deciding the project parameters for pre-embedded mine blocks
in such a way that they are attractive to the bidders and achieve the goal of
extraction of minerals from mine blocks. The pre-embedded mine blocks are
expected to get good response. The process will save time in commencement of
mining projects and deal with the issues of development of backward areas. Since
government is involved in obtaining the clearances, the community may find
the project more trustworthy and support it. The success of these mine blocks will open the doors
for government participation in other development projects also. So this is a
welcome move by the government.
***
Note:
Readers are requested to share their thoughts and post in the comment
box of
this blog to improve the content for the benefit of society. IT is also requested to
share with those who are interested in the development of mining industry.
Disclaimer: The views expressed here are of writer only and do not belong or express
views to any organization, person associated with.
|
Comments
1. The level or reliability of State Govt data on Feasibility aspect? State will also provide land for Plant construction ..?? It's not clear.
2. The bidder now needs to go very concieously once after detailed analysis of the project since the Govt will make R& R plan , PH replies, EIA on his behalf.
3. My worry is - now auction process will get more delayed due to lack of manpower with State and land acquisition is also to be done by State.
Overall it's a good move ...let's hope for the best ..
I also have the same concerns as you & Mr. Amit.
Now the State Government has to engage professionals to carry out these work, which seems to be a time taking considering lengthy government procedures.
The quality of all reports are to be watched.
But yes, sure of one thing that we will be moving from conventional to highly professional.
Rather I should thank you for writing this blog in very simple language.
subsequent relative comments from Mr Amit regarding feasibility report prepared by State Govt. and land requirements not only for plant establishments but the rail line connectivity most importantly in terms of logistics should be the part of pre embedded requirements for the project.
The Casino. 12 Casino Drive, Uncasville, CT 06382, United States. Driving 울산광역 출장마사지 Directions. 김제 출장안마 Directions to The Casino - 수원 출장마사지 Uncasville, 광명 출장샵 CT. Directions to 세종특별자치 출장마사지